dc.description |
FUTURE CENTURY lIMITED( App)
Vs
TAN ESCO(Res) |
|
dc.description |
The National Service Construction Department (NSCD) was contracted
to build 25 blocks of eight apartments for residential occupation by
employees of the President's office at Kijitonyama Makumbusho area. The
NSCDalso contracted the appellant to supply, install, test and commission
power supply to the blocks (Exhibit P.l). The respondent's obligation, as it
has always been" was to supply and distribute electricity into the blocks. The
appellant did the work. |
|
dc.language |
en |
|
dc.publisher |
CAT-DAR ES SALAAM |
|
dc.subject |
Breach of contract |
|
dc.title |
Future Century Ltd..Appe Vs Tanesco..Respo Civil Appe No.5 Of 2009 Hon.Kimaro,J.A |
|
dc.type |
Other |
|